\section{Schedule Driver} The milestones of the \acs{AHEPaM} project are listed in table \ref{tab:milestones} \begin{table} \begin{center} \begin{tabular}{ |c|c|c|c|c| } \hline Date & Name & WP/Deliverable & Attendencies & Comments \\ \hline 16.02.22 & KoM & n/a & CAU/ESA & \\ 4.04.22 & Requirements Discussion & n/a & CAU/ESA & \\ 12.05.22 & Requirements Discussion & n/a & CAU/ESA & \\ June 2023 & submission for DM PRR/DR & TN 1-11, MAM 1-3 & CAU & \\ July 2023 & DM DR & n/a & CAU/ESA & planned \\ \hline \end{tabular} \caption{Milestones of the \acs{AHEPaM} project} \label{tab:milestones} \end{center} \end{table}