\documentclass[12pt]{article} \usepackage{fullpage} \usepackage[utf8]{inputenc} \usepackage{graphicx} \usepackage{hyperref} \usepackage{xcolor} \usepackage{subcaption} \usepackage{multirow} \author{P. Kühl} \title{AHEPaM Assembly procedure} \begin{document} \maketitle This procedures describes the assembly of the AHEPaM DM/FM. \newline Section 1 gives some clarifications/definitions regarding the naming scheme.\newline The procedure is split in three parts, \begin{itemize} \item Detector assembly (section 2, 4 weeks total) \item Preamp board assembly (section 3, 3 weeks total (1.5 weeks for DM)) \item final assembly (section 4, 2 weeks total) \end{itemize} \section{Clarifications / definitions} The detector set-up can be seen in fig. \ref{fig:telescope-specs}. This includes the positions and naming scheme of the SSDs (SSD-A till SSD-E). For the Cherenkov detectors and the BGOs, in the following we will name \begin{itemize} \item BGO-1: the BGO in-between SSD-B and SSD-C \item BGO-2: the BGO in-between SSD-C and SSD-D \item CHKV-1: the Cherenkov in-between SSD-A and SSD-B \item CHKV-2: the Cherenkov in-between SSD-D and SSD-E. \end{itemize} The E-Box and Board set-up is depicted in fig. \ref{fig:ebox-board-stack}. In the following we will name \begin{itemize} \item base-frame: upper segment of the E-Box. The detectors are mounted on top of the base-plate, the Preamp-Boards are housed in this segment \item filter-frame: middle segment of the E-Box. This segment houses the Shaper-/Filter-boards \item backend-frame: lower segment of the E-Box. This segment houses the Analog, LVPS, HVPS boards. \item Revisionsopening: open segments of filter-frame for Jumper-Harness assemblies \end{itemize} \begin{figure}[h] \begin{subfigure}[]{0.5\linewidth} \includegraphics[width=\linewidth]{cau-ath-ddc-0006_i1-0/media/cau-ath-icd-0009_i2-0_telescope.pdf} \caption[FM telescope]{\centering{FM telescope}} \label{fig:techdraw-fm-telescope} \end{subfigure} \hfill \begin{subfigure}[]{0.5\linewidth} \includegraphics[width=\linewidth]{cau-ath-ddc-0006_i1-0/media/cau-ath-icd-0009_i2-0_detectors.pdf} \caption[FM detectors]{\centering{FM detectors}} \label{fig:techdraw-fm-detectors} \end{subfigure} \caption[Two side by side pages showing the FM telescope]{Details of the FM telescopes. - taken from ddf-0006} \label{fig:telescope-specs} \end{figure} \begin{figure}[h!] \centering \includegraphics[width=0.75\linewidth]{cau-ath-ddc-0006_i1-0/media/athena_stacked-boards.png} \caption[CAD-View showing AHEPaMs ebox' board arrangement.]{FM-AHEPaM's electronics boards' arrangement: Preamp-PCBs (red) on top, followed by filter/ shaper-PCBs (green). The backend-PCBs are located at the bottom (blue). - taken from ddf-0006} \label{fig:ebox-board-stack} \end{figure} \section{Detector assembly} \subsection{BGOs} BGOs, part 1 \hfill \textbf{1 week total} \begin{itemize} \item install BGO1 into chassis \hfill day 1 \item install BGO2 into chassis \hfill day 1 \item testing BGO1 in chassis in to-build Keksdose \hfill day 2 \item testing BGO2 in chassis in to-build Keksdose \hfill day 3 \end{itemize} \vspace{5mm} BGOs, part 2 \hfill \textbf{1 week total} \begin{itemize} \item screw SSDB and SSDC on BGO1 \hfill day 1 \item testing SSDB and SSDC in to-build Keksdose \hfill day 1 \item screw SSDD on BGO2 \hfill day 1 \item testing SSDD in to-build Keksdose \hfill day 1 \item staking + curing side 1 of BGO1 (screws and cables) \hfill day 2 \item staking + curing side 2 of BGO1 (screws and cables) \hfill day 3 \item staking + curing side 1 of BGO2 (screws and cables) \hfill day 2 \end{itemize} \subsection{Cherenkovs} Cherenkovs, part 1 \hfill \textbf{1 week total} \begin{itemize} \item install CHKV1 into chassis \hfill day 1 \item install PMT to CHKV1 \hfill day 1 \item install PMT/HV-Board to CHKV1 \hfill day 1 \item install CHKV2 into chassis \hfill day 2 \item install PMT to CHKV2 \hfill day 2 \item install PMT/HV-Board to CHKV2 \hfill day 2 \item soldering, washing, inspection, documentations for CHKV1+CHKV2 \hfill day 3+4 \item install cover for PMT/HV \hfill day 4 \end{itemize} \vspace{5mm} Cherenkovs, part 2 \hfill \textbf{1 week total} \begin{itemize} \item screw SSDA on CHKV1 (strain relief cables with Kaptontape) \hfill day 1 \item screw SSDB on CHKV2 (strain relief cables with Kaptontape) \hfill day 1 \item testing SSDA+CHKV1 in to-build Keksdose \hfill day 1 \item testing SSDE+CHKV2 in to-build Keksdose \hfill day 2 \item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 3 \item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 4 \item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 5 \end{itemize} \subsection{Merging with base frame} Mounting detectors on base-frame \hfill \textbf{1 day total} \begin{itemize} \item Base-frame in assembly jig \item mount BGO1 on BGO bracket \item mount BGO2 on BGO bracket \item mount BGO bracket on base-frame, thread the cables to lower side (strain relief cables with Kaptontape) \item mount CHKV1 and CHKV2 on base-frame, thread the cables to lower side (strain relief cables with Kaptontape) \end{itemize} \section{Preamp board assembly} \subsection{PreAmp-Boards 1+2} Integration of PreAmp-Boards 1+2 \hfill \textbf{1 week total} \begin{itemize} \item fold over assembly jig for PreAmp-Board 1+2 assembly \item PreAmp1: shorten cables, Kapton tape wires, soldering, inspection, washing \hfill day 1-3 \item PreAmp2: shorten cables, strip (abisolieren), Kapton tape wires, soldering, inspection, washing \hfill day 4-6 \item staking + curing PreAmp1+PreAmp2 cables \hfill day 7 \item screw PreAmp1+PreAmp2, staking + curing screw \hfill day 7 \end{itemize} \subsection{PreAmp-Boards 3+4} Integration of PreAmp-Boards 3+4 \textcolor{red}{(obsolete for DM!)} \hfill \textbf{1 week total} \begin{itemize} \item fold over assembly jig for PreAmp-Board 3+4 assembly \item PreAmp3: shorten cables, Kapton tape wires, soldering, inspection, washing \hfill day 1-3 \item PreAmp4: shorten cables, strip (abisolieren), Kapton tape wires, soldering, inspection, washing \hfill day 4-6 \item staking + curing PreAmp3+PreAmp4 cables \hfill day 7 \item screw PreAmp3+PreAmp4, staking + curing screws \hfill day 7 \end{itemize} \subsection{Base-frame cable management, testing(?)} Cable management on base-frame \hfill \textbf{2 days total} \begin{itemize} \item positioning, fixation, staking + curing of all wires on the base-frame \item \textcolor{red}{testing?} \end{itemize} \section{final assembly} \subsection{Integration Shaper-/Filter-Boards} Shaper-Boards assembly \hfill \textbf{2 days total} \begin{itemize} \item shaper-boards 1-4 in filter-frame (handfest) \hfill day 1 \item put filter-frame on base-frame - use PreAmp sockets as positioning, torquen \hfill day 1 \item staking + curing \hfill day 1+2 \item \textcolor{red}{Gehäuseschrauben?} \end{itemize} \subsection{Integration ANA-formfactor Board in backend-frame} Integration ANA-board in backend-frame \textbf{(Bottom plate remains open!)} \hfill \textbf{1 day total} \begin{itemize} \item Insert ANA-formfactor board in backend-frame, torquen \hfill day 1 \item staking + curing of screws \hfill day 1 \end{itemize} \subsection{Integration of backend-frame} The intragration of the backend-frame requires up to 3 persons \hfill \textbf{1.5 weeks total} \begin{itemize} \item insert Jumper-Harness 1-4 in ANA-board, torquen \hfill day 1 \item staking + curing of screws \hfill day 2 \item thread Jumper-Harness 1-4 through Revisionsopening \hfill day 3 \item merge backend-frame and upper segments, connect via housing-screws \hfill day 3 \item connect Jumper-Harness 1-4 with Shaper-Boards, torquen \hfill day 3 \item fold over assembly jig for thread of cable loop \hfill day 3 \item staking + curing of Jumper-Harness in shaper-boards \hfill day 5 \item staking + curing of Jumper-Harness screws in shaper-boards \hfill day 5 \item Mounting, staking + curing Revisionscover \hfill day 5 \item fold over assembly jig for next orientation \hfill day 6 \item staking + curing of cable loop Jumper-Harness at backend-frame \hfill day 6 \item fold over assembly jig for next orientation \hfill day 7 \item assemble bottom plate with screws, staking + curing of screws\hfill day 7 \end{itemize} \end{document}