1
0
Fork 0
overleaf-AHEPaM/procedures/assembly.tex
2023-09-20 22:04:10 +00:00

188 lines
No EOL
8.5 KiB
TeX

\documentclass[12pt]{article}
\usepackage{fullpage}
\usepackage[utf8]{inputenc}
\usepackage{graphicx}
\usepackage{hyperref}
\usepackage{xcolor}
\usepackage{subcaption}
\usepackage{multirow}
\author{P. Kühl}
\title{AHEPaM Assembly procedure}
\begin{document}
\maketitle
This procedures describes the assembly of the AHEPaM DM/FM. \newline
Section 1 gives some clarifications/definitions regarding the naming scheme.\newline
The procedure is split in three parts,
\begin{itemize}
\item Detector assembly (section 2, 4 weeks total)
\item Preamp board assembly (section 3, 3 weeks total (1.5 weeks for DM))
\item final assembly (section 4, 2 weeks total)
\end{itemize}
\section{Clarifications / definitions}
The detector set-up can be seen in fig. \ref{fig:telescope-specs}. This includes the positions and naming scheme of the SSDs (SSD-A till SSD-E). For the Cherenkov detectors and the BGOs, in the following we will name
\begin{itemize}
\item BGO-1: the BGO in-between SSD-B and SSD-C
\item BGO-2: the BGO in-between SSD-C and SSD-D
\item CHKV-1: the Cherenkov in-between SSD-A and SSD-B
\item CHKV-2: the Cherenkov in-between SSD-D and SSD-E.
\end{itemize}
The E-Box and Board set-up is depicted in fig. \ref{fig:ebox-board-stack}. In the following we will name
\begin{itemize}
\item base-frame: upper segment of the E-Box. The detectors are mounted on top of the base-plate, the Preamp-Boards are housed in this segment
\item filter-frame: middle segment of the E-Box. This segment houses the Shaper-/Filter-boards
\item backend-frame: lower segment of the E-Box. This segment houses the Analog, LVPS, HVPS boards.
\item Revisionsopening: open segments of filter-frame for Jumper-Harness assemblies
\end{itemize}
\begin{figure}[h]
\begin{subfigure}[]{0.5\linewidth}
\includegraphics[width=\linewidth]{cau-ath-ddc-0006_i1-0/media/cau-ath-icd-0009_i2-0_telescope.pdf}
\caption[FM telescope]{\centering{FM telescope}}
\label{fig:techdraw-fm-telescope}
\end{subfigure}
\hfill
\begin{subfigure}[]{0.5\linewidth}
\includegraphics[width=\linewidth]{cau-ath-ddc-0006_i1-0/media/cau-ath-icd-0009_i2-0_detectors.pdf}
\caption[FM detectors]{\centering{FM detectors}}
\label{fig:techdraw-fm-detectors}
\end{subfigure}
\caption[Two side by side pages showing the FM telescope]{Details of the FM telescopes. - taken from ddf-0006}
\label{fig:telescope-specs}
\end{figure}
\begin{figure}[h!]
\centering
\includegraphics[width=0.75\linewidth]{cau-ath-ddc-0006_i1-0/media/athena_stacked-boards.png}
\caption[CAD-View showing AHEPaMs ebox' board arrangement.]{FM-AHEPaM's electronics boards' arrangement: Preamp-PCBs (red) on top, followed by filter/ shaper-PCBs (green). The backend-PCBs are located at the bottom (blue). - taken from ddf-0006}
\label{fig:ebox-board-stack}
\end{figure}
\section{Detector assembly}
\subsection{BGOs}
BGOs, part 1 \hfill \textbf{1 week total}
\begin{itemize}
\item install BGO1 into chassis \hfill day 1
\item install BGO2 into chassis \hfill day 1
\item testing BGO1 in chassis in to-build Keksdose \hfill day 2
\item testing BGO2 in chassis in to-build Keksdose \hfill day 3
\end{itemize}
\vspace{5mm}
BGOs, part 2 \hfill \textbf{1 week total}
\begin{itemize}
\item screw SSDB and SSDC on BGO1 \hfill day 1
\item testing SSDB and SSDC in to-build Keksdose \hfill day 1
\item screw SSDD on BGO2 \hfill day 1
\item testing SSDD in to-build Keksdose \hfill day 1
\item staking + curing side 1 of BGO1 (screws and cables) \hfill day 2
\item staking + curing side 2 of BGO1 (screws and cables) \hfill day 3
\item staking + curing side 1 of BGO2 (screws and cables) \hfill day 2
\end{itemize}
\subsection{Cherenkovs}
Cherenkovs, part 1 \hfill \textbf{1 week total}
\begin{itemize}
\item install CHKV1 into chassis \hfill day 1
\item install PMT to CHKV1 \hfill day 1
\item install PMT/HV-Board to CHKV1 \hfill day 1
\item install CHKV2 into chassis \hfill day 2
\item install PMT to CHKV2 \hfill day 2
\item install PMT/HV-Board to CHKV2 \hfill day 2
\item soldering, washing, inspection, documentations for CHKV1+CHKV2 \hfill day 3+4
\item install cover for PMT/HV \hfill day 4
\end{itemize}
\vspace{5mm}
Cherenkovs, part 2 \hfill \textbf{1 week total}
\begin{itemize}
\item screw SSDA on CHKV1 (strain relief cables with Kaptontape) \hfill day 1
\item screw SSDB on CHKV2 (strain relief cables with Kaptontape) \hfill day 1
\item testing SSDA+CHKV1 in to-build Keksdose \hfill day 1
\item testing SSDE+CHKV2 in to-build Keksdose \hfill day 2
\item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 3
\item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 4
\item staking + curing side 1 of CHKV1 and CHKV2 (screws and cables) \hfill day 5
\end{itemize}
\subsection{Merging with base frame}
Mounting detectors on base-frame \hfill \textbf{1 day total}
\begin{itemize}
\item Base-frame in assembly jig
\item mount BGO1 on BGO bracket
\item mount BGO2 on BGO bracket
\item mount BGO bracket on base-frame, thread the cables to lower side (strain relief cables with Kaptontape)
\item mount CHKV1 and CHKV2 on base-frame, thread the cables to lower side (strain relief cables with Kaptontape)
\end{itemize}
\section{Preamp board assembly}
\subsection{PreAmp-Boards 1+2}
Integration of PreAmp-Boards 1+2 \hfill \textbf{1 week total}
\begin{itemize}
\item fold over assembly jig for PreAmp-Board 1+2 assembly
\item PreAmp1: shorten cables, Kapton tape wires, soldering, inspection, washing \hfill day 1-3
\item PreAmp2: shorten cables, strip (abisolieren), Kapton tape wires, soldering, inspection, washing \hfill day 4-6
\item staking + curing PreAmp1+PreAmp2 cables \hfill day 7
\item screw PreAmp1+PreAmp2, staking + curing screw \hfill day 7
\end{itemize}
\subsection{PreAmp-Boards 3+4}
Integration of PreAmp-Boards 3+4 \textcolor{red}{(obsolete for DM!)} \hfill \textbf{1 week total}
\begin{itemize}
\item fold over assembly jig for PreAmp-Board 3+4 assembly
\item PreAmp3: shorten cables, Kapton tape wires, soldering, inspection, washing \hfill day 1-3
\item PreAmp4: shorten cables, strip (abisolieren), Kapton tape wires, soldering, inspection, washing \hfill day 4-6
\item staking + curing PreAmp3+PreAmp4 cables \hfill day 7
\item screw PreAmp3+PreAmp4, staking + curing screws \hfill day 7
\end{itemize}
\subsection{Base-frame cable management, testing(?)}
Cable management on base-frame \hfill \textbf{2 days total}
\begin{itemize}
\item positioning, fixation, staking + curing of all wires on the base-frame
\item \textcolor{red}{testing?}
\end{itemize}
\section{final assembly}
\subsection{Integration Shaper-/Filter-Boards}
Shaper-Boards assembly \hfill \textbf{2 days total}
\begin{itemize}
\item shaper-boards 1-4 in filter-frame (handfest) \hfill day 1
\item put filter-frame on base-frame - use PreAmp sockets as positioning, torquen \hfill day 1
\item staking + curing \hfill day 1+2
\item \textcolor{red}{Gehäuseschrauben?}
\end{itemize}
\subsection{Integration ANA-formfactor Board in backend-frame}
Integration ANA-board in backend-frame \textbf{(Bottom plate remains open!)} \hfill \textbf{1 day total}
\begin{itemize}
\item Insert ANA-formfactor board in backend-frame, torquen \hfill day 1
\item staking + curing of screws \hfill day 1
\end{itemize}
\subsection{Integration of backend-frame}
The intragration of the backend-frame requires up to 3 persons \hfill \textbf{1.5 weeks total}
\begin{itemize}
\item insert Jumper-Harness 1-4 in ANA-board, torquen \hfill day 1
\item staking + curing of screws \hfill day 2
\item thread Jumper-Harness 1-4 through Revisionsopening \hfill day 3
\item merge backend-frame and upper segments, connect via housing-screws \hfill day 3
\item connect Jumper-Harness 1-4 with Shaper-Boards, torquen \hfill day 3
\item fold over assembly jig for thread of cable loop \hfill day 3
\item staking + curing of Jumper-Harness in shaper-boards \hfill day 5
\item staking + curing of Jumper-Harness screws in shaper-boards \hfill day 5
\item Mounting, staking + curing Revisionscover \hfill day 5
\item fold over assembly jig for next orientation \hfill day 6
\item staking + curing of cable loop Jumper-Harness at backend-frame \hfill day 6
\item fold over assembly jig for next orientation \hfill day 7
\item assemble bottom plate with screws, staking + curing of screws\hfill day 7
\end{itemize}
\end{document}